Weekly Construction Update

Welcome to the ITC Construction Weekly Update. Each week, we’ll share what crews accomplished, what’s planned for the week ahead, and changes to traffic, parking, sidewalks or access to homes and businesses. We want you to know what is happening nearby and have time to plan around construction. This email complements our monthly ITC Updates newsletter, which covers the overall program.

Construction Progress & What’s Ahead

Market/Florence Mobility Hub

Last Week – through November 13
Fencing and gates are now in place around the construction site. Crews continued surveying and preparing the buildings for demolition. Electricity and water have been safely shut off to the building on site, and preparation for hazardous materials removal, known as abatement, began.

This Week – Week of November 16
Surveying will continue, abatement will begin at the building, and SoCal Gas is scheduled to shut off gas service to the site. Heavy equipment is expected to arrive early in the week. Demolition may begin toward the end of the week, starting on the north side of the building.

Market/Manchester Mobility Hub

Last Week – through November 13
Fencing and gates are now in place around the construction site. Crews continued surveying and preparing the building for demolition.

This Week – Week of November 16
Surveying and utility disconnections will continue. Abatement work to remove hazardous materials is also scheduled to begin inside the building as preparations for demolition move forward.

Work hours Monday–Saturday, 7 a.m.–7 p.m., unless otherwise noted.

Schedules are subject to change. We will share updates about changes that affect traffic, parking or access.

Managing Dust & Preparing for Demolition

Dust control will be part of our team’s daily construction operations. To keep dust under control, crews will use measures including:

  • Wetting materials before handling and during demolition and loading.
  • Watering or covering exposed soil and stockpiles.
  • Covering truckloads.
  • Cleaning affected streets and sidewalks.

Removing Hazardous Materials Before Demolition

Before demolition, crews will remove identified hazardous materials through a process called abatement. This work follows federal, state and local requirements for containing, handling and disposing of these materials to protect workers and the surrounding community.

Depending on the work, crews may enclose work areas, control airflow, keep materials wet, and use equipment with special filters (HEPA-filtered equipment) to capture fine particles. Removed materials will be properly packaged and disposed.

Stay in Touch!

Check back here for ongoing updates, follow us on social media, and sign up for the ITC monthly newsletter.

Questions or concerns, please email Info@InglewoodTransitConnector.com
Or call the ITC Hotline: (424) 799-1989

Connect With Us
Sign Up for Updates
@InglewoodTransitConnector

@itcchampions

Community input doesn’t end here

Attend upcoming meetings, participate in workshops, sign up for project updates, or contact the project team with questions or feedback. Your voice continues to help shape the future of the ITC.